Water treatment plant Jirkov 150 l/s
Year of installation: 2012
Client: SMP CZ, a.s., HST Hydrosystemy, s.r.o.
Operator: SČVK, a.s.
Client: SMP CZ, a.s., HST Hydrosystemy, s.r.o.
Operator: SČVK, a.s.
Dissolved air flotation (DAF) was newly installed and put into operation at the Písek WTP (150 l/s). The filtration stage was also reconstructed by installing the Leopold drainage system with a total area of 98 m2.